Electron Economics · Source-Based Market Intelligence  ·  Last updated: Jun 2026

The AI Data Center Cost Stack —
three markets, three margin dynamics.

AI data center capex is not one cost curve. It is three stacked markets: GPU-heavy IT spend (~53% of all-in), margin-rich powered infrastructure (~15% of capex but 20–30% OEM margins), and low-margin civil delivery risk (~4%). The remaining ~29% is engineering, permitting, and commissioning — fragmented across specialists. The investment opportunity is not where the dollars are largest. It is where scarcity, margin, and contractual leverage overlap.

Layer 1 · IT Equipment
~$17.50/W
GPU servers, networking, storage. All-in basis. ~53% of $32.75/W midpoint (46–64% across source range). Tenant-owned in colo.
~$1,650M per 100 MW
Layer 2 · Powered Shell
~$4–5/W
UPS, switchgear, cooling, generators. Facility-only basis. OEM margin pool.
~$400–500M per 100 MW
Layer 3 · Physical Shell
~$1–1.5/W
Civil structure, envelope, fit-out. Smallest % share vs non-AI equivalent.
~$100–150M per 100 MW
Gap · Design / Contingency
~$9.50/W
Engineering, permitting, contingency, commissioning, logistics. Not supplier revenue.
~$950M per 100 MW · 29% of all-in
All-in $/W — IT equip + facility + gap. Layer 1 uses this basis. Facility-only $/W — shell + MEP only, excl. IT equipment. Layers 2–3 use this basis. Shell-only $/W — civil + powered shell; what colo operators pay (no IT fit-out) Tenant fit-out — IT equipment only; JLL: up to $25M/MW on top of shell in colo AI $M / 100 MW = $/W × 100 — always
View mode:
Executive = 8-row summary · Component Detail = full breakdown with sources
Layer / Component AI all-in $/W $M / 100 MW % of all-in OEM margin Lead time Signal
Layer 1 — IT Equipment  · All-in $/W basis · tenant-owned in colo
GPU / AI servers + networking + storage
Accelerators, HBM, NVLink, interconnect, NVMe
~$17.50/W ~$1,650M ~53%
midpoint; 46–64% range
Nvidia captures GPU
pass-through for operator
~4–16 wk Dominates stack
Layer 2 — Powered Shell  · Facility-only $/W · OEM margin pool
Electrical back-end
UPS, switchgear, transformers, generators, substation
~$2.1/W ~$210M ~6.4% 22–30%
Eaton 30% · Vertiv 22.3%
40–80 wk
switchgear; 18+ mo genset
Lead time risk
Cooling
Chillers, CDU/liquid cooling, CRAH (air-cooled only), towers, pumps
~$2.3/W ~$230M ~7.0% 22–25%
Trane ~25% · Vertiv 22%
18–30 wk
chillers; CDU varies
AI-mandatory CDU
White space fit-out
Server racks, PDUs, busbars, cabling
~$0.6/W ~$60M ~1.8% 20–30%
Legrand 20.7% · Eaton 30%
6–12 wk Stable supply
Powered shell subtotal ~$4–5/W ~$400–500M ~15% 22–30%
Layer 3 — Physical Shell  · Facility-only $/W · EPC margin 4–8%
Civil structure + envelope + fit-out + site works
Steel frame, cladding, earthworks, GC prelims
~$1–1.5/W ~$100–150M ~4% 4–8%
EPC/GC margin
Parallel to MEP Smallest share in AI
Gap / Overhead  · ~$9.50/W · 29% of all-in · not supplier revenue
Design, engineering, contingency, commissioning, logistics
Fragmented across specialists: engineering firms, commissioning agents, owner's reps, permitting consultants — low-scalability margin pool
~$9.50/W ~$950M ~29% Fragmented margin pool
Total — all-in AI basis ~$27.50–38/W ~$2,750–3,800M 100%
Full source registry & methodology notes

Primary sources

Epoch AI (May 2026) — 1 GW AI facility $38B upfront capex; servers 60% of TCO annualised. epoch.ai ↗

Lean Research (Mar 2026) — Infrastructure layer split: gray space 29%, white space 10%, cooling 32% of infra; UPS 16%, switchgear 11%, transformers ~2%, chillers 9%, CRAHs 12%; AI vendor revenue $3.1–3.5M/MW vs $1.2M/MW non-AI; shell 7% / $1.90/W (400 MW AI).

Turner & Townsend DCCI 2025 — Cost category split: GC/prelims 10%, shell & core 14%→9%, mechanical 22%→33%, electrical 54%→48% (air-cooled → liquid-cooled AI). Liquid cooling premium +7–10%. Lead time data. turnerandtownsend.com ↗

JLL Global Data Center Outlook 2026 — Non-AI shell+core $11.3M/MW global avg; 7% CAGR 2020–2025; avg lead time 33 wks (+50% from 2020).

DLR 10-K 2024 — Colo pipeline ~$9.5M/MW; premium markets ~$12M/MW.

McKinsey (2026) — Switchgear: 80 wk hyperscale lead. Transformer: 50 wk lead.

Dell'Oro Group (Jan 2026) — Liquid cooling market: "nearly doubled in 2025, approaching $3B"; ~$7B by 2029.

Earnings filings used as supplier proxies

Eaton 8-K (Feb 26 2026) — Electrical Americas Q4 2025: $3.5B revenue (+21% YoY, +15% organic); 29.8% op margin (Q1 2025 record: 30.0%); DC orders +200% Q4 2025; $15.3B backlog.

Vertiv 8-K (Oct 22 2025) — Q3 2025: $2.676B revenue (+29% YoY); $9.5B backlog; book-to-bill 1.4x; 22.3% adj op margin (+220 bps); orders +60% YoY.

Cummins 8-K (Feb 5 2026) — Power Systems FY2025: $7.5B revenue (+16%); 22.7% EBITDA (+430 bps); DC revenue $3.5B/yr run rate; order book to 2028; $150M MN expansion.

Trane Technologies 8-K (Jan 29 2026) — Americas CHVAC applied bookings +120% Q4 2025 (2nd consecutive >100%); $7.8B backlog; Stellar Energy acquired.

ABB Q4 2025 press release (Jan 29 2026) — Electrification Q1 2025: $3.825B revenue, 23.2% op EBITA; $8.69B record backlog; DC "very strong double-digit" orders Q4; 800VDC partnership with Nvidia.

Legrand FY2025 press release (Feb 12 2026) — Total €9.48B (+9.6%); DC revenue ~€2.4B (26% of group); +~40% organic DC growth; 20.7% adj op margin; DC CAGR +19% since 2019.

Arista Networks Q4 FY2025 (Feb 12 2026) — Implied FY2025 ~$9B revenue (Q4 $2.488B +28.9% YoY); GAAP gross margin 63–65%.

Schneider Electric FY2025 (Feb 26 2026) — Energy Management €33.1B (+10.3% organic); DC demand "triple-digit YoY" in Q4 2025. Secure Power (UPS+PDU) not separately disclosed.

EE channel checks — Eaton AlphaSense expert sessions (EE, May 2026): enterprise architect (5–8→30–50 kW rack density; Eaton Brightlayer BMS); EPC VP (40–60 wk enterprise switchgear; modular construction −20–30% schedule). EE Centerview BTM session (May 2026): Permian 105–115°F; LSTK vs GMP contract structure. Channel check data marked EE↑ in source buttons.

Confidence system

⬤ Primary Single primary document directly states the figure.

◎ EE est. Cross-triangulated from multiple sources; not single-primary-sourced. Treat as directional.

○ EE↑ Previously EE est.; upgraded using named EE research session evidence.

Third-party market research firm TAM estimates (MarketsandMarkets, Mordor Intelligence, GMInsights, etc.) excluded — methodology not disclosed, figures not reproducible. Not investment advice.

Electron Economics · Source-Based Market Intelligence  ·  Last updated: Jun 2026

Build Cost Vintage Trend

Global average shell & core construction cost for non-AI air-cooled hyperscale (30–50 MW IT load). 7% CAGR 2020–2025. AI liquid-cooled premium: add +7–10%. Source: JLL Global Data Center Outlook (annual); Turner & Townsend DCCI 2025.

2020
$7.7M/MW
baseline
2021
~$8.3M/MW
+~8%
2022
~$8.9M/MW
+15% (T&T)
2023
~$9.5M/MW
+~7%
2024
~$10.1M/MW
+9% (T&T)
2025
$10.7M/MW
+5.5% (T&T)
2026E
$11.3M/MW
+6% (JLL)
7% CAGR 2020–2025 (JLL). From $7.7M to $10.7M/MW. Driven by construction labour inflation (+15% peak in 2022), equipment escalation (transformers, switchgear), and increasing MEP density requirements. 2025 showed deceleration (+5.5% vs +9% in 2024) — T&T notes sector-wide construction inflation of 4.2% in 2025. AI premium (not in JLL/T&T non-AI index): liquid-cooled AI facilities carry +7–10% construction premium vs equivalent air-cooled (T&T 2025). All-in with IT equipment: $27.50–38/W (Lean Research / Epoch AI).
Lead time trajectory (JLL 2026): Average equipment lead time now 33 weeks globally — up 50% from pre-2020 levels. More than half of 2025 projects experienced 3+ month construction delays. Cost inflation is decelerating; schedule risk is not improving. Switchgear: 80 wk hyperscale (McKinsey). Transformers: 50 wk (McKinsey). Generators >2 MW: 18+ months, order book to 2028 (Cummins Q4 2025 8-K). The binding constraint is electrical procurement, not civil works.
Component / metric 20202022 20242025 2026E YoY trend Source
Shell & core (non-AI global avg)
$7.7M/MW~$8.9M/MW ~$10.1M/MW$10.7M/MW $11.3M/MW +7% CAGR JLL 2026; T&T DCCI 2025. 2022: T&T +15% peak. 2024: T&T +9%. 2025: T&T +5.5% (decelerating). 2021/2023 interpolated at 7% CAGR — EE est.
Avg equipment lead time
All categories, global
~22 wks~26 wks ~30 wks33 wks 33–36 wks +50% from 2020 JLL 2026: "average equipment lead times reaching 33 weeks, a 50% increase from 2020." Prior years: EE est.
Switchgear (hyperscale)
~40 wks~55 wks ~75 wks80 wks 80+ wks Worsening McKinsey (2026): 80 wk hyperscale. EE↑ Eaton AlphaSense EPC VP: 40–60 wk enterprise (EE, May 2026). Prior years: EE est.
Transformer (MV, dry-type)
~30 wks~38 wks ~48 wks50 wks 50–55 wks Worsening McKinsey (2026). GOES steel = binding physical constraint. Korean challengers (HD Hyundai, Hyosung) gaining share. Prior years: EE est.
Generator >2 MW
~9 mo~12 mo ~16 mo18+ mo 18–24 mo Worsening Cummins Q4 2025 8-K: order book to 2028; $150M MN expansion. Prior years: EE est.
Liquid cooling CDU market
Global revenue
~$0.4B~$0.8B ~$1.8B~$3B ~$4B Accelerating Dell'Oro Group (Jan 2026): "nearly doubled in 2025, approaching $3B"; forecast ~$7B by 2029. 2020–2024: EE est. interpolated.
T&T construction cost inflation YoY
Non-AI air-cooled DC
+15% +9%+5.5% +5–6%E Decelerating T&T DCCI 2025: "+5.5% increase in cost per watt, markedly lower than 9.0% in 2024." Broader construction: +4.2% (T&T GCMI 2025). 60% of respondents expect +5–15% in 2026.
Sources: JLL Global Data Centre Outlook (2026) · Turner & Townsend DCCI 2025 · McKinsey (2026) · Cummins Q4 2025 8-K · Dell'Oro Group (Jan 2026). Years 2021, 2023 interpolated at 7% CAGR from JLL anchors — EE est. Not investment advice. electroneconomics.substack.com
Electron Economics · Source-Based Market Intelligence  ·  Last updated: Jun 2026 · T&T DCCI 2025 · v16 QA pass

Geography — $/W by Market

Shell & core construction cost per watt, air-cooled hyperscale 30–50 MW IT load. Add +7–10% for liquid-cooled AI. Source: Turner & Townsend Data Centre Construction Cost Index 2025 (primary; FX avg Oct 2024–Oct 2025). CBRE demand signals for context only. Click column headers to sort.

How to use for underwriting: Take the $/W below as your shell & core baseline. Add +7–10% for liquid-cooled AI (T&T 2025). The AI all-in estimate column (shell + $17.50/W IT + $9.50/W gap) is a screening figure only — the gap/overhead does not stay fixed across Tokyo, Singapore, Phoenix, and NoVA. In-market engineering cost, permitting complexity, labour rates, and logistics premiums vary substantially. Use the AI all-in column for relative ranking, not for project underwriting. For site-specific underwriting, adjust using local labour indices and apply T&T DCCI market differentials. Colo operators pay shell cost only — JLL notes AI tenant fit-out adds up to $25M/MW on top of shell.
View:
Market Shell $/W
T&T 2025 baseline
vs NoVA
% delta
AI all-in est.
shell+IT+contingency
Demand
signal
Market view
underwriting signal
Key constraint
Key underwriting read-through: The Cost Build tab's NoVA/DFW baseline understates costs in Tokyo (+34%), Singapore (+28%), Zurich (+26%), and Silicon Valley (+18%). It overstates in Charlotte (−16%), Columbus (−13%), Phoenix (−13%). For cross-market deal comparison, apply the delta from this table before benchmarking $/W assumptions.
Sources: Turner & Townsend Data Centre Construction Cost Index 2025 (52 markets; shell & core only; air-cooled 30–50 MW IT; FX avg Oct 2024–Oct 2025). CBRE Global Data Center Trends 2025 (demand / pricing signals). JLL 2026 Global Data Center Outlook. EE Centerview BTM session (May 2026) — Permian temperature data. AI all-in estimate = shell $/W + $17.50/W IT equipment + $9.50/W contingency/engineering — see Cost Build tab for full decomposition. Not investment advice.
Electron Economics · Source-Based Market Intelligence  ·  Last updated: Jun 2026

The powered shell is ~15% of capex —
but where 20–30% OEM margins live.

Equipment OEMs serving data center infrastructure earn manufacturer-grade margins (20–30%) on products sold into projects where EPC contractors earn 4–8%. The powered shell (~$4–5/W) is the investable layer — small in $/W but high in margin density. All figures from public earnings filings.

⬤ OEM Operating Margins — from Public Earnings Filings (2025–2026)

Compare to EPC / GC margin: 4–8% (EE Centerview BTM session, May 2026; CoVolt/EPC analysis). The gap between OEM margin and EPC margin is structural — OEMs hold no delivery risk after purchase order; EPCs absorb schedule delay; developers warehouse financing cost on deferred commissioning.

Eaton · Electrical Americas
25.6%
Q1 2026 op. margin (Q2 guided 22.6–23.0% — further dip before H2 recovery)
DC orders +240% Q1 · revenue +50% · $14.5B backlog · exit 2026 above 30%
Boyd Thermal: $1.7B 2026 rev; raises DC addressable market to $3.4M/MW
Beam Rubin DSX platform (collab. with NVIDIA, debut Q1 2026): purpose-built power distribution for GB200/Rubin-generation AI racks
Mobility spin-off: Q1 2027 — immediately margin-accretive post-close
Eaton Q1 2026 8-K, May 5 2026 · Eaton Q1 2026 earnings call
Vertiv · Total Company
20.8%
Adj. operating · Q1 2026 (+430 bps YoY) · Q2 guided 20.7–21.7%
$15B+ backlog (+109% YoY) · Q4 2025 orders +252% · Americas Q1 organic +44%
FY2026 raised: $13.5–14.0B (+29–31% organic) · adj. EPS +51% YoY
ThermoKey acq. (EMEA thermal mgmt, exp. Q2 2026 close)
Vertiv Q1 2026 8-K, Apr 22 2026
Cummins · Power Systems
29.5%
Power Systems EBITDA · Q1 2026 record (FY2025: 22.7%)
Power Systems Q1: $2.0B (+19% YoY) · NA power gen +23% · total company revenues +3% to $8.4B
FY2026 Power Systems guidance: 25–26% EBITDA · total company EBITDA guided 17.0–18.0%
$50B 2030 revenue target (Analyst Day) · low-pressure fuel cell sold to Alstom Q1 2026
Cummins Q1 2026 8-K, May 5 2026
Trane · Americas CHVAC
~25%+
Adj. operating · applied bookings +160% Q1 2026 (3rd consecutive >100%)
Record $10.7B backlog (+70% YoY) · book-to-bill 150%
Stellar Energy: $1B backlog, ~$1B biz in 2–3 yrs (CEO)
Trane Q1 2026 earnings call, Apr 30 2026
ABB · Electrification
23.5%
Op. EBITA · Q1 2026 (+320 bps YoY) · Electrification $4.6B (+21%)
Total ABB Q1 2026: $8.7B (+18%) · FCF $1.3B (strongest ever Q1)
Raised 2026 guidance: high single to low double-digit growth
ABB Q1 2026 results, Apr 22 2026
Legrand · Data Center
20.7%
Adj. op. margin · Q1 2026 (unchanged at 20.7%) · +18% total sales Q1 2026
DC acquisitions: Keydak (China racks, €60M+) + TES (UK power, €85M, majority DC)
FY2026 target: +10–15% sales growth · DC CAGR +19% since 2019
Legrand Q1 2026 results, Apr 2026
Schneider · Energy Mgmt
~19%
Adj. EBITA guidance FY2026: 19.1–19.4% (group level)
Q1 2026: €9.77B revenue (record); EM €8B (+12.8% organic)
DC double-digit gains Q1; Secure Power (UPS+PDU) not separately disclosed
Schneider Electric Q1 2026 results, Apr 30 2026
⬤ EPC / GC margin for comparison: 4–8% — EE Centerview BTM diligence session (May 2026); CoVolt/EPC analysis. EPCs absorb delivery schedule risk; OEMs collect margin and move to next order. Note: Eaton Q1 2026 EA margin (25.6%); Q2 2026 guided 22.6–23.0% (further dip before H2 recovery); management targets exit above 30% in H2 and 32% by 2030. Mobility segment spin-off targeted Q1 2027 — immediately margin-accretive post-close. Cummins Power Systems Q1 2026 EBITDA 29.5% — a new record. Schneider Electric: FY2026 group-level adj. EBITA guidance 19.1–19.4% (Secure Power not separately disclosed). Arista Networks: GAAP gross margin ~63–65% FY2025.
The architecture transitions to watch:
800VDC: Schneider (800VDC sidecar, Apr 2025) and ABB (Nvidia partnership, Jan 2026) are both moving toward 800VDC architecture. Only 15–25% of facilities on 800VDC by 2030 (Lean Research). Direction is set — UPS content risk is real but slow-moving.
CRAH → CDU (accelerating): CRAH is 12% of infra in non-AI builds; physically obsolete above 41 kW/rack. Vertiv, Schneider, and now Eaton (acquired Boyd Thermal, Mar 2026 — liquid cooling; Boyd Q1 revenue 2×+ YoY, backlog doubled in 6 months) are all competing in CDU. Trane's Stellar Energy ($1B backlog; CEO: "$1B business in 2–3 years"). CDU market ~$3B 2025 (Dell'Oro). The CDU competitive set is now wider than ever — Vertiv, Schneider, Eaton, Trane, JCI, plus specialists (Submer, LiquidStack, GRC).
Cummins fuel cell: Cummins sold its low-pressure fuel cell business to Alstom (Q1 2026). Bloom Energy remains the BTM fuel cell wildcard — Cummins is now a pure generator play.
Bottom line: Backlogs are at record levels across every OEM — Vertiv $15B+, Trane $10.7B, Eaton EA $14.5B. Cummins Power Systems hit a record 29.5% EBITDA in Q1 2026. Eaton's Q1 margin dip (25.6% vs 30% prior record) is a ramp-cost story, not a demand story. The question is whether these margins are structural or scarcity rents — GOES steel and generator capacity constraints still point to 2027+ before normalisation begins. Watch Boyd Thermal integration progress and Korean transformer challenger share gains as the leading indicators.
Component Market leaders Challengers / disruption Market proxy (filing-based) OEM margin AI architecture signal
Layer 1 — IT Equipment
GPU / AI servers
Nvidia (~80%+ AI GPU), Supermicro (GB200), Dell, HPE AMD, Intel; ODM trend (Meta, Google) Nvidia DC: ~$44B annualised (Q1 FY2026 $13.5B ×4) Pass-through; facility operator does not capture margin
Networking
Nvidia/Mellanox (IB), Arista, Broadcom Cisco, Juniper; Ethernet AI fabric challenge to IB Arista FY2025 ~$9B (Q4 $2.488B +28.9% YoY) 63–65%
Arista GAAP GM
IB dominance at 5-yr risk; Broadcom Ethernet gaining
Layer 2a — Electrical (Gray Space)
UPS systems
Schneider, Vertiv, Eaton ABB, Huawei, Legrand (Keor) Vertiv Critical Power ~$5.5B; Schneider EM €33.1B (Secure Power unsplit) 22–30%
Eaton 30% / Vertiv 22.3%
⚠ 800VDC content risk — Schneider + ABB both partnering with Nvidia on 800VDC architecture
Switchgear
Schneider, Eaton, ABB Siemens, Powell Industries ABB Electrification Q1 2025: $3.825B rev; Eaton EA $13.4B FY2025 (all electrical) 23–30%
ABB 23.2% / Eaton 30%
80 wk lead times; GOES steel bottleneck on transformers; Korean challengers gaining share
Backup generators
Caterpillar, Cummins mtu, Generac; Bloom Energy (fuel cell BTM) Cummins Power Systems FY2025: $7.5B revenue; DC $3.5B/yr run rate 22.7%
Cummins EBITDA
Order book to 2028; 18+ mo lead; Bloom Energy fuel cell emerging for BTM prime power
Layer 2b — White Space
PDUs / busways
Legrand (Starline 6,000A), Eaton, Vertiv nVent (Enlogic), Schneider Legrand DC ~€2.4B FY2025; Q1 2026: +18% total sales, 20.7% margin; Keydak + TES acquisitions 20.7%
Legrand adj. op.
Busway displacing fixed copper (GPU refresh reconfigurability); Vertiv CoolChip Max hybrid CDU-PDU (Feb 2026)
Layer 2c — Cooling
Chillers
Carrier, Trane Technologies, JCI Daikin, Airedale, Stulz Trane Q4 2025: $7.8B backlog; applied bookings +120% Q4 2025 ~25%+
Trane Americas CHVAC
Trane DSX to 145°F ambient. JCI offloaded residential HVAC to Bosch ($8.1B) to focus on DC cooling
CRAH / CRAC units
Vertiv, Schneider, Stulz Airedale, Rittal Vertiv thermal ~$3.5B est. (proxy: Vertiv $10.2B × ~35%) ~22%
at risk
⚠ Most structurally challenged category. Physics ceiling at 41 kW/rack. Vertiv + Schneider pivoting to CDU to protect revenue
Liquid cooling — CDUs
Vertiv, Schneider, Eaton (Boyd Thermal, acq. Mar 2026), JCI (Silent-Aire) AAON/BASX ($2.13B backlog, +107% YoY; liquid cooling +187% TTM), Trane (Stellar Energy), Submer, LiquidStack, GRC, Asetek ~$3B (2025, Dell'Oro); ~$7B by 2029 ~22–25%
incumbent proxy
Fastest-growing category. AAON/BASX (specialist): $2.13B backlog (+107% YoY), BASX liquid cooling +186.8% TTM, book-to-bill >2× for 4 consecutive quarters, FY2026 revenue +40–45% — fastest organic growth rate in segment (AAON Q1 2026 8-K, May 7 2026). Eaton acquired Boyd Thermal (Mar 2026) — liquid cooling; Boyd Q1 2026 revenue 2×+ YoY, backlog doubled in 6 months, adds $1.7B+ to Eaton 2026 revenue. Trane Stellar Energy: $1B backlog; CEO: "$1B business in 2–3 years." JCI Silent-Aire CDU (Sep 2025). Vertiv CoolChip Max hybrid CDU-PDU (Feb 2026). Competitive set now 5+ major incumbents plus specialists — OCP standardisation lowers specialist barrier.
Layer 3 — Civil / EPC
EPC / GC
Turner, Kiewit, AECOM Skanska, Jacobs, Matrix Service ENR Top 400 DC category (no precise TAM) 4–8%
GC/EPC margin
Absorbs schedule delay from long-lead electrical equipment. LSTK on power plant side; GMP on data hall
Margin data from public earnings filings only: Eaton 8-K (Feb 2026) · Vertiv 8-K (Oct 2025) · Cummins 8-K (Feb 2026) · Trane 8-K (Jan 2026) · ABB Q4 2025 press release (Jan 2026) · Legrand FY2025 (Feb 2026) · Arista Q4 FY2025 (Feb 2026) · Schneider FY2025 (Feb 2026). Market sizing from public company revenue disclosures and Dell'Oro Group (Jan 2026). Third-party market research firm TAM estimates excluded. Not investment advice. electroneconomics.substack.com
Electron Economics · Source-Based Market Intelligence  ·  Last updated: Jun 2026

AI Infrastructure — 12 Charts

All charts derived from primary sources in the Cost Build, OEM Margins, Vintage Trend, Geography, and Demand tabs. Hover any element for data detail.

1 — Capex Flow & Margin Pool
$32.75/W all-in AI capex decomposed. Bar width = $/W; bar below = OEM margin. Powered shell = 15% of capex, 22–30% OEM margins.
The powered shell (~$4.50/W) carries 22–30% OEM margins on 15% of all-in capex. IT equipment is the dominant spend but a pass-through — facility operators do not capture GPU margin.
2 — T&T Cost Category Shift (Air → Liquid AI)
Mechanical share nearly doubles (22%→33%). Electrical shrinks (54%→48%). Shell falls (14%→9%). Source: T&T DCCI 2025.
Mechanical share nearly doubles (22%→33%) when moving from air-cooled to liquid-cooled AI. Shell & core shrinks (14%→9%). This is the structural shift driving CDU demand and CRAH displacement.
3 — OEM Margin vs EPC Gap
Equipment OEMs earn 20–30% on products sold into projects where EPCs earn 4–8%. Q1 2026 most recent. All from public filings.
Equipment OEMs earn 20–30% operating margins on products sold into projects where EPCs earn 4–8%. The gap is structural: OEMs hold no delivery risk post-PO; EPCs absorb schedule delay.
4 — OEM Order Backlog (Q1 2026)
Record backlogs across all six OEMs — demand is contracted, not forecast. Vertiv $15B+, Trane $10.7B, Eaton EA $14.5B.
Backlogs are contracted, not forecast. Vertiv $15B+ and Eaton EA $14.5B represent 12–18 months of forward revenue at current run rates. Demand is visible; execution is the risk.
5 — Build Cost Trend 2020–2026E
Non-AI shell & core global average. 7% CAGR 2020–2025. 2025 deceleration to +5.5%. 2026E: $11.3M/MW (+6%). JLL 2026; T&T DCCI 2025.
Construction cost inflation is decelerating (+5.5% in 2025 vs +9% in 2024). But lead times are not improving — schedule risk and cost risk are moving in opposite directions.
6 — Equipment Lead Time Progression
Switchgear 80 wk, transformers 50 wk, generators 78 wk — all worsening. Average +50% from 2020. Cost inflation decelerating; lead times are not. McKinsey (2026); JLL 2026.
Switchgear (80 wk) and generators (78 wk) are the binding programme constraints, not civil works. Cost per watt is stabilising; schedule slip is not. Interconnection queue is a separate and often longer constraint.
7 — Supply Chain Risk Matrix
Lead time (x) vs $/W (y). Bubble size = OEM margin %. Red dashed = architecture risk. Top-right = primary underwriting constraints.
Top-right quadrant = highest underwriting risk. CRAH (red dashed) is structurally obsolete above 41 kW/rack. Liquid cooling CDU (blue) is mandatory for AI but in a less consolidated market.
8 — Component $/W: Non-AI vs AI vs Colo
Facility-only $/W for key powered shell components across three facility types. Lean Research (Mar 2026); T&T 2025.
CRAH is the starkest shift: ~$0.40/W in non-AI, ~$0.15/W in AI as liquid cooling displaces it. Liquid cooling CDU is the inverse — new in AI, near-zero in non-AI. The architecture has changed at the physics level.
9 — Shell $/W by Market
14 markets ranked. Baseline = NoVA $11.5/W (used in Cost Build tab). Tokyo +34% premium; Charlotte −16%. T&T DCCI 2025.
NoVA (baseline) understates costs by 34% in Tokyo and 18% in Silicon Valley. It overstates by 16% in Charlotte — the fastest-growing US data center market by new supply.
10 — Hyperscaler Capex 2022–2026E
Big Five combined: ~$162B (2022) → ~$345B (2025, company rows) → ~$745B (2026E, company-guided). Microsoft $190B confirmed FY26 Q3 earnings (Apr 2026). 72% CAGR since Q2 2023. Q4 2025: $140.6B. Note: 2025 aggregate uses company rows ($345B); prior Futurum/Introl $448B estimate was a broader market figure — not directly comparable.
Big Five 2026E: ~$745B (company-guided; Microsoft $190B confirmed FY26 Q3, Apr 2026). 2025 company rows sum to $345B. 72% CAGR since Q2 2023. Q4 2025: $140.6B in a single quarter. This is the demand engine behind every supply chain constraint in the other charts.
11 — Liquid Cooling Market Growth
CDU/DLC market: ~$0.4B (2020) → ~$3B (2025) → ~$7B (2029E). Nearly doubled in 2025. Fastest-growing component category. Dell'Oro Group (Jan 2026).
CDU/liquid cooling doubled in 2025 to ~$3B (Dell'Oro), driven by AI rack densities exceeding the 41 kW/rack air cooling ceiling. Dell'Oro forecasts ~$7B by 2029. Incumbents and specialists are competing simultaneously.
12 — Rack Density by Facility Type
Air cooling ceiling: 41 kW/rack (physics limit). Enterprise AI: 30–50 kW. Hyperscale AI: 120–150 kW. GB200 NVL72: 120–130 kW. Rubin Ultra: ~600 kW forward.
The 41 kW/rack air cooling ceiling is a physics limit, not an economic preference. GB200 NVL72 at 120–130 kW is already 3× above it. Rubin Ultra at ~600 kW will require purpose-built CDU infrastructure from the ground up.
IT / Hyperscaler
Stable / growing
Moderate risk
High risk / obsolescence
EPC / civil
All charts derived from primary sources in respective tabs. Lead times: McKinsey (2026) · JLL 2026. Margins: public earnings filings (Q1 2026). Build cost: JLL 2026; T&T DCCI 2025. Liquid cooling: Dell'Oro Group (Jan 2026). Hyperscaler capex: Epoch AI / Futurum / company guidance. Not investment advice. electroneconomics.substack.com
Electron Economics · Source-Based Market Intelligence  ·  Last updated: Jun 2026 · Company guidance as of Q1 2026 earnings

Hyperscaler & Neocloud Capex Forecast

The demand side of the cost table. Big Five hyperscalers guided ~$745B combined 2026 capex (company-guided). Neoclouds and AI-native builders add $50-60B+ on top. Bars scaled to Amazon 2026 ($200B = 100%). All figures from public earnings guidance and named company announcements. Jun 2026.

Reading this tab: 2024 and 2025 = reported or preliminary; 2026 = company guidance as of Jun 2026. Hyperscaler capex includes IT equipment, facility, and leasehold — not directly comparable to the facility-only $/W in the Cost Build tab. Neocloud spend-to-revenue ratios of 2–3× are common during buildout phase. Not revenue forecasts.
JLL 2026 supercycle read-through: $3 trillion total investment required through 2030. 100 GW new capacity; global capacity doubles to 200 GW. Key inflection 2027: AI inference overtakes training as dominant workload — shifting demand from centralised hyperscale clusters toward distributed regional hubs. This changes the geographic demand pattern: secondary and tertiary markets gain share. Americas retain ~50% of global capacity. APAC: 32 GW → 57 GW. 77% of current construction pipeline pre-committed; global occupancy 97%. Lease rates CAGR ~5% through 2030.
Source: JLL 2026 Global Data Center Outlook (Jan 2026) · DCD (Mar 2026) · Bisnow (Jan 2026)
Entity Type 2024 capex 2025 capex 2026 guided YoY 25-26 Key focus / note Source
Sources: Amazon FY2025 earnings (Feb 2026) - Alphabet FY2025 earnings (Feb 2026) - Microsoft FY2026 annualised rate - Meta FY2026 guidance (Jan 2026) - Oracle FY2026 guidance - CoreWeave Q4 2025 earnings call (Mar 2026) - xAI Southaven $20B announcement (Jan 2026); CNBC (Jun 2026) - Futurum Group (Feb 2026) - Introl (Jan 2026) - Goldman Sachs hyperscaler forecast - Epoch AI via Visual Capitalist (Apr 2026) - JLL 2026 Global Data Center Outlook (Jan 2026): $3T supercycle, 100 GW, 2027 inference inflection. All 2026 figures = company guidance or analyst consensus as of Jun 2026. Not investment advice. electroneconomics.substack.com
Electron Economics · Source-Based Market Intelligence · Last updated: Jun 2026

OEM Intelligence — Competitive Positioning by Component

Who owns what share of each powered shell component market. Two display modes: revenue-anchored share where primary data exists (CDU, generators, PDU, transformers), and competitive positioning where segment revenue is not separately disclosed. All figures from public earnings filings unless marked otherwise. Confidence tier shown on each card.

Powered shell TAM est.
~$400–500M
per 100 MW AI facility · Lean Research 2026
OEM margin range
20–30%
vs EPC/GC 4–8% on same project · public filings Q1 2026
Highest margin OEM
29.5%
Cummins Power Systems EBITDA · Q1 2026 record
Fastest growing segment
CDU / Liquid
AAON/BASX +186.8% TTM · Dell'Oro $3B→$7B by 2029
⬤ Primary Revenue figure from named public filing
◎ Triangulated Derived from multiple sources; directional
○ Positioning Qualitative assessment; no primary revenue denominator
Leader Gaining Holding At risk Emerging
Architecture risk read-through: The three components most at risk from structural transitions are CRAH units (physics obsolescence above 41 kW/rack — air cooling ceiling), UPS systems (800VDC architecture migration compresses traditional UPS content; Schneider + ABB both partnering Nvidia on 800VDC), and chillers (liquid cooling reduces chiller content per MW in AI-dense builds). Components with no architecture risk but supply constraint: switchgear (80 wk lead, GOES steel), transformers (50 wk lead, Prolec GE + Korean challengers), generators (18+ mo lead, Cummins order book to 2028).
Revenue figures: Vertiv Q1 2026 8-K · Cummins Q1 2026 8-K · Legrand Q1 2026 · ABB Q1 2026 · Eaton Q1 2026 · GE Vernova Q1 2026 · AAON Q1 2026 · Dell'Oro Group (Jan 2026) · Gartner UPS market share (2024, triangulated). Market TAM estimates for UPS/switchgear/chillers are EE triangulations from segment revenue disclosures — not primary TAM figures. Segment revenue where not separately disclosed is noted as positioning only. Not investment advice. electroneconomics.substack.com
Electron Economics · Source-Based Market Intelligence · Last updated: Jun 2026

Changelog — What Changed and Why

Every data update, structural change, and source addition since the first version. All changes are sourced from public earnings filings, named analyst reports, or EE channel checks. No version removes data — superseded figures are noted with their replacement.

NewFirst time this data appears
UpdateExisting figure replaced with newer filing
FixError corrected
StructureUI / tab / layout change
v16 Jun 2026 Update New
Update
GE Vernova Q1 2026 — Prolec GE + $163B backlog + 17.8% EBITA — Total backlog $116B → $163B (+$13B sequentially, incl. $5B Prolec GE). Gas turbine: 83 → 100 GW under contract; target ≥110 GW by year-end 2026. Electrification DC equipment orders: $2.4B in Q1 2026 alone — more than all of 2025 combined. Electrification EBITDA margin +590 bps to 17.8%. Prolec GE (transformer mfr): $5B backlog, ~$3B 2026 revenue, 20%+ EBITDA. Updated: substation drawer, transformer drawer.
GEV Q1 2026 8-K, Apr 22
New
AAON/BASX — added as specialist CDU challenger — Q1 2026: BASX-branded DC cooling sales +72.4% to $228.6M; total backlog $2.13B (+107% YoY, +16.5% sequentially); liquid cooling sales +186.8% TTM; book-to-bill >2× for 4th consecutive quarter. CEO targets ~$1B BASX revenue 2026. FY2026 guidance raised to +40–45% revenue growth — fastest organic growth rate in the CDU segment. Added to: liquid cooling source drawer, OEM tab CDU competitive note.
AAON Q1 2026 8-K, May 7
Update
Vertiv — Q2 2026 guidance + ThermoKey acquisition + raised FY guide — Q2 2026 adj. operating margin guided 20.7–21.7% (+270 bps YoY). FY2026 net sales raised to $13.5–14.0B (organic +29–31%). Americas Q1 organic +44%. ThermoKey acquisition expected Q2 2026 close — strengthens EMEA thermal management. Adj. EPS guidance +51% YoY at midpoint.
Vertiv Q1 2026 8-K, Apr 22
Update
Big Five capex total — $688B → $745B — Microsoft confirmed $190B CY2026 at Q1 2026 earnings (was $133B in prior version — a $57B gap). Big Five aggregate updated accordingly. Microsoft demand card corrected.
Microsoft FY26 Q3 earnings call (Apr 2026); internal QA
New
Eaton Beam Rubin DSX platform — Eaton debuted the Beam Rubin DSX platform in collaboration with NVIDIA at Q1 2026 earnings. Purpose-built power distribution for GB200/Rubin-generation AI racks. Validates Eaton as a grid-to-chip player for the next GPU architecture cycle.
Eaton Q1 2026 earnings call, May 5
Fix
Cummins — Power Systems vs total company EBITDA clarified — Card previously showed 29.5% EBITDA as if it were a company-wide figure. Clarified: 29.5% is Power Systems segment EBITDA (Q1 2026 record); total company EBITDA guided at 17.0–18.0% for FY2026. Power Systems segment FY2026 guidance: 25–26% EBITDA.
Cummins Q1 2026 8-K, May 5; internal QA

v15 Jun 2026 Update New
New
JLL $3T supercycle (Demand tab) — New aggregate card: $3T total investment 2026–2030 ($1.2T real estate + $870B debt + $1–2T IT fit-out). 100 GW new capacity; global capacity doubles to 200 GW. 2027 inflection: inference overtakes training, shifting demand toward distributed regional hubs. AI workloads: 25% (2025) → 50% (2030).
JLL 2026 Outlook
New
Schneider Electric — 7th OEM margin card — Group-level adj. EBITA guidance 19.1–19.4% FY2026. Q1 2026: record €9.77B revenue (+11.2% organic); Energy Management €8B (+12.8% organic). Secure Power (UPS + PDU) still not separately disclosed — noted explicitly.
Schneider Q1 2026, Apr 30
Update
Eaton — Q2 2026 guidance added to margin card — Q2 Electrical Americas guided 22.6–23.0% (below Q1's 25.6% — further dip before H2 recovery). Boyd Thermal raises DC addressable market to $3.4M/MW. Mobility segment spin-off targeted Q1 2027, immediately margin-accretive post-close.
Eaton Q1 2026, May 5
Update
Legrand — updated to Q1 2026 + two DC acquisitions — Q1 2026: +18% total sales (+9.3% organic); 20.7% margin unchanged. Keydak (China rack mfr, €60M+) and TES (UK power distribution, €85M, majority DC revenue) acquired Q1 2026. FY2026 target: +10–15% sales growth. DC revenue: €0.7B (2020) → €2.4B (FY2025) → >€2.6B est. 2026E.
Legrand Q1 2026, Apr
New
CDU cost anchor — $4.5–5.2M/MW (Liquid cooling drawer) — First primary-sourced $/MW figure for the CDU layer specifically. Air-cooled heat rejection: ~$1.8M/MW. Liquid-cooled AI halls: $4.5–5.2M/MW including CDUs, secondary pumping loops, and dry coolers. AI-optimised facilities at 40–80 kW rack density: ~$20M/MW (excl. IT + land).
Archdesk / JLL Apr 2026

v14 Jun 2026 Fix Structure
Fix
IT share math corrected — Previous versions stated "GPU silicon ~60% of all-in." Corrected to ~53% at the $32.75/W midpoint (46–64% across the $27.50–38/W source range). The 60% figure was only valid at the $27.50/W lower bound.
Internal QA
Structure
Executive / Component Detail toggle (Cost Build) — Default view is now an 8-row executive summary (layer-level). Full component breakdown available via "Component Detail" toggle. Reduces cognitive load on first open.
UX review
New
Basis dictionary — Four explicit definitions added: All-in $/W, Facility-only $/W, Shell-only $/W, and Tenant fit-out. Replaces the thin basis badge that previously confused readers mixing facility-owner and tenant cost bases.
UX review
Fix
Geography sort bug fixed — sortDir was toggling after sorting, causing the sort direction indicator to lag by one click. Now updates before sorting.
Code review
New
Market attractiveness score (Geography tab) — Each market now has a derived underwriting signal: Strong (Charlotte, Columbus, Atlanta), Good (Frankfurt, Paris, Portland, Madrid, Phoenix), Caution (NoVA, Chicago, Dublin, Singapore), Constrained (Tokyo, Zurich, Silicon Valley, Amsterdam). Sortable column.
EE analysis
New
Geography Shell / AI all-in toggle — Switch the primary $/W column between shell-only (T&T 2025 baseline) and all-in AI estimate (shell + $17.50/W IT + $9.50/W contingency).
UX review
Structure
Chart interpretation lines (Analytics tab) — One-sentence analytical read-through added below each of the 12 canvases. The most important: rack density chart — "The 41 kW/rack air cooling ceiling is a physics limit, not an economic preference."
UX review
Structure
Demand classification badges — Each demand entity now shows its status: Committed (Stargate JV), Company guided (hyperscalers, CoreWeave), Announced (xAI). All dated Jun 2026.
UX review
Structure
URL hash routing + resize handler — Tab state now reflected in URL (#cost, #oem, #analytics etc.) so tabs are shareable links. Charts redraw on window resize.
Bug fix
Structure
OEM tab headline — H1 changed to: "The powered shell is ~15% of capex — but where 20–30% OEM margins live." The previous title described the section rather than stating the thesis.
UX review
Structure
Source buttons renamed ? → Src — "?" implied uncertainty; "Src" signals a deliberate source reference. ARIA labels added to all 12 canvases and all source buttons.
Accessibility / UX

v13 Jun 2026 New Update
New
Demand Forecast tab — Big Five hyperscaler 2026 guided capex: Amazon $200B, Alphabet $180B, Microsoft $133B, Meta $125B, Oracle $50B. Total $688B (+88% vs 2024). Neoclouds: CoreWeave $32B, xAI $20B, Stargate JV $100B. Goldman Sachs: $5.3T Big-4 FY2025–2030. Epoch AI: $448B combined 2025 at 72% CAGR since Q2 2023.
Company guidance / Futurum / Goldman / Epoch AI
New
Analytics tab expanded from 2 → 12 charts — Added: T&T cost category shift, OEM margin vs EPC gap, OEM backlog, build cost trend 2020–2026E, lead time progression, component $/W by facility type, 14-market $/W ranked bar, hyperscaler capex stacked area, liquid cooling market growth, rack density range. All 12 watermarked ELECTRON ECONOMICS.
EE analysis / primary sources

v12 Jun 2026 Update
Update
Q1 2026 earnings — all OEM margin cards refreshed — Cummins Power Systems: 22.7% (FY2025) → 29.5% EBITDA (Q1 2026 record, +430 bps). ABB Electrification: 23.2% (Q1 2025) → 23.5% Q1 2026 (+320 bps); $4.6B revenue. Trane: $7.8B → $10.7B backlog (+70% YoY); applied bookings +160% Q1 2026 (3rd consecutive quarter >100%). Vertiv: 22.3% (Q3 2025) → 20.8% Q1 2026; backlog $9.5B → $15B+. Eaton: 30% → 25.6% Q1 2026 (temporary; 12-factory ramp; exits 2026 above 30%).
Q1 2026 8-Ks, Apr–May 2026
New
Eaton Boyd Thermal acquisition (Mar 2026) — Eaton enters liquid cooling. Boyd Q1 revenue 2×+ YoY; backlog doubled in 6 months. Added to CDU competitive set alongside Vertiv, Schneider, Trane (Stellar), JCI.
Eaton Q1 2026, May 5
New
Cummins — fuel cell business sold to Alstom (Q1 2026) — Cummins is now a pure generator play. Bloom Energy remains the BTM fuel cell wildcard. Updated architecture callout and generator OEM competitive note.
Cummins Q1 2026, May 5
New
Eaton CEO market data — 32 GW of DC capacity under construction in US (70% AI); 228 GW total DC pipeline = "12 years of backlog at 2025 build rates." Added to reconciliation row source drawer.
Eaton Q1 2026 earnings call

v11 Jun 2026 New
New
12 Substack article links across all tabs — In-line ↗ chips added to source drawers linking relevant EE Substack pieces: The Diesel Genset Decade, The Price of a GPU Hour, CoreWeave's Contract Machine, Bloom Energy × Compute, Equinix Part 2, The Tariff Lottery, OpenAI's Energy Problem, Gas Turbine Reservations. Related reading boxes on OEM, Geography, Vintage, Analytics, and Demand tabs.
electroneconomics.substack.com

v9–v10 Jun 2026 Structure
Structure
Executive UX rebuild (v9) — New headline: "AI data center capex is not one cost curve — it is three stacked markets." Four KPI layer cards above the table (IT $17.50/W / Shell $4–5/W / Civil $1–1.5/W / Gap $9.50/W). Basis badge strip. Source [?] collapsible drawers replacing dense inline source cells. Expandable footnote registry. Geography: cards replaced with JS-sortable table. Eaton HTML bug fixed (missing closing div). Sticky first column removed (mobile double-scroll).
UX review
New
Analytics tab — first 2 charts (v10) — Chart 1: Capex flow and margin pool (Sankey-style). Chart 2: Supply chain risk bubble matrix (lead time × $/W × OEM margin). Both Canvas-based, no external libraries, ELECTRON ECONOMICS watermark.
EE analysis

v8 Jun 2026 Update New
New
ABB and Legrand — OEM margin cards added (5th + 6th) — ABB Electrification: 23.2% op. EBITA Q1 2025; $8.69B record backlog; 800VDC partnership with Nvidia. Legrand Data Center: 20.7% adj. operating FY2025; DC €2.4B (26% of group); +40% organic 2025; CAGR +19% since 2019.
ABB Q4 2025 / Legrand FY2025
Update
Networking row — Arista FY2025 ~$9B primary source — Previously showed "~$30B DC" (third-party TAM). Replaced with Arista Networks FY2025 implied revenue ~$9B (Q4 $2.488B, +28.9% YoY); GAAP gross margin 63–65%.
Arista Q4 FY2025, Feb 12
Update
PDU row — Legrand DC €2.4B primary source — Previously had no credible primary source. Legrand FY2025 DC revenue is now the primary market proxy for the white space layer (PDUs, busbars, cable management).
Legrand FY2025, Feb 12
Update
Trane — $10.7B backlog, +160% applied bookings (Q1 2026) — Previous: $7.8B backlog, +120% Q4 2025. Third consecutive quarter of applied bookings >100%. Stellar Energy: $1B backlog; CEO: "$1B business in 2–3 years."
Trane Q1 2026, Apr 30

v6–v7 Jun 2026 New Structure
New
Vintage Trend tab — 2020–2026E build cost trajectory ($7.7M → $11.3M/MW; 7% CAGR). Lead time worsening: switchgear 40 → 80 wk; generators 9 mo → 18+ mo. Liquid cooling CDU market growth: $0.4B (2020) → $3B (2025). T&T inflation YoY: +15% (2022), +9% (2024), +5.5% (2025) — decelerating. Key thesis: cost inflation decelerating; schedule risk is not.
JLL 2026 / T&T DCCI 2025 / McKinsey 2026
New
Geography tab — 14 markets with T&T 2025 $/W. Tokyo $15.2/W (most expensive globally) through Charlotte $9.5/W. NoVA/DFW used as baseline in Cost Build tab — Geography tab shows the delta.
T&T DCCI 2025 / CBRE 2025
Structure
Light mode / warm beige palette (v7) — Previous versions used dark (#0e0e0e) background. Changed to warm beige (#faf8f4) across all surface tokens, text tokens, accent colours, and pill backgrounds. Dark mode explicitly rejected.
Design decision

v1–v5 Jun 2026 Structure
New
Initial build — Cost Build tab — Three-column table: non-AI / AI / colo. Components across Layers 1–3 with $/W, $M/100MW, confidence pills (Primary / EE est. / EE↑). Source discipline: MarketsandMarkets, Mordor Intelligence, GMInsights, and all market research TAM firms excluded — methodology not disclosed, figures not reproducible. Only public earnings filings, T&T, JLL, Dell'Oro, Lean Research, and Epoch AI accepted as primary sources.
Lean Research / Epoch AI / T&T / JLL
New
OEM Margins tab — initial 4 margin cards — Eaton Electrical Americas 30% (Q1 2025 record), Vertiv 22.3% (Q3 2025), Cummins Power Systems 22.7% (FY2025), Trane Americas CHVAC ~25%+. All from named 8-K filings. Core insight: equipment OEMs earn 22–30% margins on products sold into projects where EPCs earn 4–8%.
Eaton / Vertiv / Cummins / Trane 8-Ks
Fix
Math reconciliation established (v5) — IT ($17.50/W) + Powered shell ($4.50/W) + Civil ($1.25/W) = $23.25/W. Gap to all-in: $9.50/W = 29% of $32.75/W midpoint. Named explicitly as structurally embedded overhead — not a rounding error. Derived from Epoch AI $38B/GW and Lean Research $27.50/W (400 MW) anchors.
Epoch AI / Lean Research
All version changes sourced from public earnings filings, named consultant reports, or EE channel checks. No version removes historical data — superseded figures noted with their replacement source. For methodology and full source registry, see the expandable footnote section on the Cost Build tab. Not investment advice. electroneconomics.substack.com